OREANDA-NEWS. November 16, 2010. The capital investments of “Vologdaenergo” will exceed around 48 mln Rub.

On the substation “Pahomovskaya” 35/6 kW, the pre-commissioning testing is implemented. The substation is situated in the Vitegorskiy region.  In the frames of reconstruction, 2 new power transformers 4 MVA were installed. Till the end of the next week the substation will be placed in operation.

The substitution of the obsolete equipment, repair costs minimization and   adaptation of equipment to the possible increase of capacity are the main reasons for reconstruction of substation “Pahomovskaya” 35/6 kW.

The reconstruction will increase the reliability of the electric power supply and will provide the possibility of additional capacity connection.  The capital investments of  “Vologdaenergo” will exceed around  48 mln Rub.