Titan 2 Announced Baltic NPP July Results
OREANDA-NEWS. August 16, 2012. At the construction site of the first power unit of the Baltic NPP the key event of July for the organizations of TITAN-2 Holding has become the completion of foundation plate concreting for the reactor building up to mark -7,50.
The builders from the Holding's subsidiaries have carried out the following works at the buildings and structures of the "nuclear island":
• The concreting of reactor's foundation plate from mark – 10. 95 to mark – 7.50 has been completed. In the course of works
• Vertical waterproofing of the walls of the security building and the reactor building is going on;
• In the security building, at mark – 8.80 laying of
•
The work related to arrangement of the spur railway track "
TITAN-2 Holding is the largest Group of Companies in the North-West of Russia which erects the most important facilities of nuclear industry and power engineering. It performs the full cycle of building and assembly works, from development of design documentation to the facility commissioning. The Holding consists of about 20 organizations and employs about 4,000 employees with more than 40-year-experience in construction of unique and super-complicated facilities. The Holding’s management company and the leading engineering business-unit is the Company JSC CONCERN TITAN-2.
Baltic NPP project implies construction of two power units with a 1,150 MW–reactor of WWER type and heating capacity of 250 GCal each. The design-to-life cycle of Baltic NPP is 50 years, and that of the key equipment is 60 years. The commissioning of the first power unit is scheduled for 2016, and of the second one – for 2018. The station location is the north-east of