Reliance Power Delivers Quarter of Strong Financial Performance
OREANDA-NEWS. Reliance Power Limited, a Reliance Group company, today announced its un-audited financial results for the quarter ended December 31, 2013. The company's Board of Directors approved the financial results at its meeting here today.
The Company continued its growth momentum by registering strong operational and financial performances.
Q3 FY2013-14 HIGHLIGHTS
Operating Capacities
1,200 MW Rosa Power Plant in UP operated at an availability of 97% and registered a PLF of 84% despite planned overhaul of one unit during December
2013
The 40 MW Dhursar solar PV plant in Rajasthan operated at a high PLF of 20%
The 45 MW wind project in Vashpet, Maharashtra Operated at a PLF of 12%
Capacities under Construction
• The Butibori project received provisional tariff approval from the Maharashtra Electricity Regulatory Commission (MERC) for sale of power from its entire capacity of 600 MW to Reliance Infrastructure Limited, on cost plus basis, for a period of 25 years.
The second 660 MW unit of the Sasan UMPP achieved full load in December 2013 and was commissioned in January 2014. The third 660 MW unit is also at an advanced stage of construction and expected to be commissioned in this quarter. The balance units are also expected to be commissioned in the coming months.
The work at 100 MW Concentrated Solar Power (CSP) project in Dhursar, Rajasthan is on stream and the project is expected to be commissioned by March 2014.
Reliance Power Limited, a part of the Reliance Group, is India's leading private sector power generation company. The company has the largest portfolio of power projects in the private sector based on coal, gas, hydro and renewable energy, with an operating portfolio of 3,205 megawatts. The company also has the largest captive coal reserves in the private sector, estimated at two billion tonnes. Besides, the company is developing three coal mines in Indonesia and is also developing coal bed methane blocks in India.