OREANDA-NEWS. The condenser group equipment weighs a total of over two thousand tonnes and will be installed by the specialist staff of TITAN-2, from the Holding's dedicated installation company OJSC MSU-90.

Currently, the specialist of the Installation and Construction Directorate No.90 (MSU-90) are working at power unit 2, preparing the site for rigging and installation of 16 spring units, in total weighing nearly 300 tonnes, which will serve as base for the condensers.

Overall during this task the installation workers will position and install in their designed positions over two thousand tonnes of equipment of upper and lower piping of the condenser group.

Turbine hall condensers are used to cool turbine units of the LNPP-2 power unit 1. Their main task is to establish and maintain vacuum rarefaction in the turbine neck, and thus inside the condenser as well.

TITAN-2 is one of the contractors involved in construction and installation works at the power units 1 and 2 of the Leningrad NPP-2. 145 construction sites are simultaneously underway at the new site of Leningrad NPP. The holding's own specialists are involved at 42 sites of the 1st and 2nd power units of LNPP-2. The works involve operations with the reactor hall, turbine, power supply, water supply and other facilities of the power units. In total, the project of new LNPP-2 comprises 270 main and auxiliary facilities.