OREANDA-NEWS  ROSSETI Volga has increased the capacity of connection to the grid of the plant in Mordovia by 1.5 times, the electric grid complex reported.

Thanks to the implemented project, a new production complex will be opened – it will be able to process up to 400 tons of milk per day.

"In order to produce an additional 2.3 megawatts, the power engineers reconstructed the switchgear at the substation feeding the enterprise and installed modern commercial electricity metering systems. All installed equipment is Russian-made. The total volume of consumer connections has reached almost 5.2 megawatts," ROSSETI said in a statement on the Maks platform.