OREANDA-NEWS.  Power Machines OJSC and TGC-11 OJSC have signed a contract to manufacture and supply equipment for turbine set No. 10 of Omskaya TPP-3.

The contract was signed following competitive negotiations on the right to supply equipment for the needs of Omskaya TPP-3. Power Machines OJSC was pronounced the winner and then awarded a contract.

According to the contract terms Power Machines are to manufacture and supply a 120 MW steam turbine complete with a turbogenerator and auxiliary equipment within the turbine plant limits to the Customer.  In addition the Power Machines specialists will supervise the installation, commissioning and startup works, as well as train the plant's operating personnel. The equipment deliveries are scheduled to be completed in February, 2015.

The new equipment supply is carried out within the framework of the replacement of a 50 MW steam turbine at turbine set No. 10 of Omskaya TPP. The turbine to be replaced was manufactured in 1963 at the Leningradsky Metallichesky Zavod, which now forms part of Power Machines OJSC.

As a result of the renovation the capacity of the power unit of Omskaya TPP-3 will rise from 50 MW to 120 MW.