OREANDA-NEWS. April 28, 2012. TO-6 of Mosmetrostroy completed the drivage of 650m long left tunnel at the Zamoskvoretskaya line Krasnogvardeyskaya – Alma-Atinskaya stations span, reported the press-centre of Mosmetrostroy.    

Canadian TBM "Lovat" was started up on January 15 to perform span construction from Proektiruemiy passage to rightabout dead ends of Krasnogvardeyskaya station. The lining rings average construction rate amounted for 8–10 rings per day. This is the eighth tunnel constructed with this TBM.

The TBM came out to the reception shaft near Krasnogvardeyskaya station dead ends breaking fencing concrete piles.

The new section commissioning is scheduled for late 2012.