OREANDA-NEWS. February 01, 2013. Karelenergo branch of IDGC of the North-West, JSC has executed 2012 investment program in full. 1 bln 163 mln RUR were allocated for implementation of the projects, which exceeds 2011 performance by 25%. The funds assigned enabled performance of works on 820 investment projects of the branch.

There are 4 facilities among the largest investment projects of Komienergo branch implemented in 2012: works on implementation of the first stage of project “Construction of 110 kV “Sokolovka – Pazhga” substation” (132 mln RUR of fixed assets commissioned), implementation of the first stage of the project for technical re-equipment of 110/10 kV “Zapadnaya” substation (62 mln RUR), reconstruction of 35/6 kV “Vorkutinskaya” substation (83 mln RUR), construction of the overhead transmission line to the Abez Settlement (298 mln RUR).

Fixed assets commissioning in 2012 made 101 per cent which is 1 bln 100 mln RUR. 161 MVA and 210 km of grids were commissioned. Commissioned capacities increment made 69 MVA and 148 km of transmission lines.