OREANDA-NEWS. The Moatize coal processing plant (CPP) in Mozambique has already reached the electro mechanic assembly stage. The civil part of the work, which began in April with the metallic structure, is scheduled to finish in July.

The assembly and implementation of the primary grinder, transport conveyer belts, CHP (Coal Handling Plant) transfer towers and forklift Stacker 3 will happen in parallel. The completion of the works, including commissioning, is estimated for November 2015.