OREANDA-NEWS. Performance stock of “NK “Yangpur” JSC obtained producing well.

In late summer -early autumn at Osenneye field “NK “Yangpur” JSC acquired oil free-flowing with current yield of 100 t upon drilling sidetrack at well No. 123s2.

New well was drilled into virgin part of the deposit down to3 548 m, at this its vertical depth is2 945 m, shifting is1 393 m, with angle down in hole of 34degrees.

Well construction was planned according to the Design document of the development of the Osenneye field, Design document being drafted by the specialists of Belnipineft. At planning future drilling site seismic data, collected earlier on, was reinterpreted. The drilling itself was preceded by deepening and transfer to extraction of well No. 823 of the same Osenneye deposit. The oil free-flowing with yield of 50 t obtained here confirmed the expected oil saturation of this section of the field.

With due account given to the new data, a decision to drill new sidetrack of well No. 123 was taken. The well was brought into production earlier, but due to water intrusion oil production on such well was suspended.

Such constructive approach to the selection of the project site for opening out of new reservoir proved fruitful - oil free-flowing of dry crude oil with current yield of 100 t.